SR 6 Emergency Bridge Rehabilitation

Steel Rehabilitation

Location:

Meadville, PA

Owner:

PennDOT District 11

General Contractor:

Advantage Steel & Construction

Completion Date:

April 2019

A portal was ripped in half on the SR 6 through truss bridge in Meadeville, PA.  Advantage steel fabricated installed temporary support systems in multiple locations, replacing portals, and vertical members throughout the bridge.   Work was performed in less than a month to open the bridge back up to traffic prior to the required completion date.

Key Construction Elements:
  • Temporary Support Systems

  • Jacking

  • Construction Engineering & Design

  • Steep Replacement

  • Fabrication

General Work Activities
  • Steel Erection

  • Steel Rehabilitation

  • Innovative Solutions

  • Temporary Support

  • Jacking

  • Demolition

  • Fabrication