top of page

Construction Projects

Tackling Unique Challenges With Expertise & Creativity

Genesee River Bridge Rehabilitation

Steel Rehabilitation

Location:

Rochester, NY

Owner:

NYSDOT

General Contractor:

The Pike Company

Completion Date:

October 2016

Advantage Steel and Construction supported and replaced over 167 bearings, under live traffic conditions, on the Genesee River Bridge. Working directly over the Genesee River, temporary support systems were created for all 167 locations, along with performing over 50 beam end repairs on the girders.  

Key Construction Elements:
  • Steel Rehab

  • Temporary Support

  • Jacking

  • Fabrication

  • Bearing Replacement

General Work Activities
  • Steel Erection

  • Steel Rehabilitation

  • Innovative Solutions

  • Temporary Support

  • Jacking

  • Demolition

  • Fabrication

bottom of page